June 17, 2021 – The provincial government will provide more than $16 million in funding to build a new recreational facility in the Township of Wellesley.
The municipality will kick in an additional $6 million for the $22 million infrastructure project.
This new facility will include an ice pad, space for both senior and youth centres, a walking track, gymnasium and two soccer pitches.
Construction is expected to begin in just over six months, with completion slated for 2023.